Schedule float
Schedule float is the amount of time an activity can slip without delaying the project end date. Zero float means the activity sits on the critical path.
Worked example
On a hypothetical warehouse, interior painting has ten days of float. Structural steel erection has zero float, so a steel delay moves substantial completion.